Current Projects

Hard hat cone

2023 Construction Projects interactive map   


We are looking for your comments on how we are doing with construction projects, let us know at: HOW ARE WE DOING?

If you have any questions or concerns about a project, please email us or call (218) 824-1110.

Reconstruction

CR 115 (Ojibwa Rd and Nashway Rd)

*project funded with local option sales tax*

Project Overview:

Project was awarded to Borden Excavating and Pratt's Affordable Excavating.  On July 26, 2022 Crow Wing County entered into a contract with Borden Excavating Inc. for the reconstruction of CR 115 from the south TH 371 intersection to the north TH 371 intersection. The project is 4.8 miles in length and will involve grading, storm sewer, curb & gutter, and resurfacing.  In 2022 a majority of the vegetation removal for the entire project was completed along with utility relocations on the south half (TH 371S to CR 127) of the project.  Utility relocations have been on-going spring 2023.

CR 115 will be closed to through traffic and a detour will be in place (see diagram to the right).  Each night the contractor will leave the road passable for local traffic. The overall schedule is subject to variability based upon weather and other factors. Please use caution when traveling near the construction zone.

Current Update:

  • 10/12/2023 - New mailbox supports between County Road 127 and East Lake Hubert Drive are scheduled for Friday, October 13, 2023.

Sign up for construction alerts through Crow Wing County Alert by scanning the code or at ALERT.

Sign-up for construction alerts using your phone camera

QRC CWC ALERT

CR 115 Detour Map

CR 115 Detour Map_041123

 CSAH 1 from Cass County Line to CSAH 66, CSAH 4 from Lakeshore Ave to CSAH 11 

CR 29 in Nisswa, CR 145 from Veterans St to CSAH 16, Dewes Rd, Ebinger Rd, Memorial Gardens Rd, Gilbert Shores Rd, Shady Ln, Woodlawn St

Project Overview:

This project has been awarded to Anderson Brothers Construction and road work is anticipated to begin in May. Once construction operations begin, weekly updates will be provided on this website. Traffic will be controlled with flaggers and/or a pilot car in the work areas. Expect delays and please use caution while traveling through the construction zone.

Current Update:

  • CSAH 1 - 05/25/2023 – Construction is now complete.
  • CSAH 4 - 06/29/2023 - Construction is now complete.
  • CR 145 – 06/16/2023 - Construction is now complete.
  • First Assessment District Roads – 06/29/2023 - Construction is now complete.
  • CSAH 29 - 07/21/2023- Paving operations now complete.

If you have any questions about this project, please contact Project Manager Steve Stroschein or call (218) 824-1110.

Project Documents:

Bituminous Reconditioning

CSAH 3 from E St to Mississippi River bridge, CSAH 5 (Beave Dam Rd) 

CSAH 49 (Wise Rd)

Project Overview:

This project has been awarded to Anderson Brothers Construction and road work is anticipated to begin in late June or early July. A project schedule will be released soon. Once construction operations begin, weekly updates will be provided on this website. Construction work on CSAH 3 and CSAH 49 will require temporary road closures. In an effort to minimize traffic disruptions, these roads will be closed at separate times.

  • CSAH 3 - Paving operations are now complete.  Road is open to traffic. 
  • CSAH 5 - Paving operations are now complete.  Road is open to traffic.
  • CSAH 49 - Paving operations are now complete.  Road is open to traffic. 

If you have any questions about this project, please contact Project Manager Steve Stroschein or call (218) 824-1110. 

Project Documents:

CSAH 3 detour map

CSAH 3 Detour Map_0

CSAH 49 Phase 1 detour map

CSAH 49 Phase 1 Detour Map_0

CSAH 49 phase 2 detour map

CSAH 49 Phase 2 Detour Map_0

Roundabout

CSAH 3/11 South of Crosslake

Project Overview:

The Crow Wing County Highway Department has entered into a contract with Anderson Brothers Construction to construct a roundabout at the intersection of County State Aid Highways (CSAH) 3 & 11, just south of Crosslake.  The work will consist of constructing a single lane roundabout, which will include curb and gutter, storm sewer, pedestrian improvements, and a lighting system.   During construction, the intersection will be closed, and a detour will be in place (see diagram to the right).  

  • The intersection of CSAH 3 and CSAH 11 IS OPEN.  A big thanks to the prime contractor Anderson Brothers Construction, the other contractors, and County staff (and the weather) for the excellent coordination to allow the opening a month ahead of schedule.  Please drive with caution as final pavement markings, final lighting, and removal of the bypass road and the detour signing will need to be done under traffic.  This was a very important safety improvement for the many users of these roadways.  

If you have any questions or comments about this project, please contact the project manager Jordan Larson or call (218) 824-1110.

Project Documents:

CSAH 3/CSAH 11 Detour Map

CSAH 3  11 Detour Map_0

Roundabout 

CSAH 31/TH 210 in Crosby

Project Overview:

This project has been awarded to Anderson Brothers Construction and road work is anticipated to begin June 19th. Weekly updates will be provided on this website. Construction operations are scheduled to be complete on September 1, 2023, weather dependent. During construction, the intersection will be closed. County Roads 12 & 28 will be used to detour traffic between Deerwood and Crosby. Local businesses will remain open and accessible during construction.

If you have any questions about this project, please contact Project Manager Steve Stroschein or call (218) 824-1110. 

  • 08/18/2023 - The roundabout will open to traffic this evening. All barricades will be removed from the roadway later today. Detour signage will be removed next Tuesday.
  • Paint striping is complete.
  • Sign installs are nearly complete. Still waiting on a few street/guide signs.
  • Misc. work remaining: Driveways, mailboxes, E911 signs, delineators, Deer Trail grading, etc.

Project Documents:

Roundabout

CSAH 48/Cypress Drive


Project Overview:

The City of Baxter has awarded this project to Kraemer Trucking, with work (tree clearing) already underway.  A detour will be set up and can be found in the link below.  Expect delays and please use caution while traveling near the construction zone.

If you have any questions about this project, please contact Scott Hedlund (SEH Project Engineer) at 612-865-3509

Current Update:

  • Beginning at 7:00 AM on Thursday, July 13th, Highland Scenic Road (CSAH 48) is planned to be closed to all traffic from approximately 100 feet east of Chestnut Drive to approximately 500 feet east of Berrywood Drive for street and underground utility work in connection with the construction of a roundabout at Cypress Drive. The roadway will be closed for 50 calendar days and is anticipated to be open by September 1, 2023. 
    Signage will be in place notifying the public of the construction activities and provide detour routes. Please drive with caution in the work zone area. 

Project Documents:

CSAH 31/TH 210 Detour Map

CSAH 31 Detour Map1024_1

CSAH 31/TH 210 Business Access Detour

CSAH 31 Business Access Map1024_1

CSAH 48/Cypress Dr. Detour Map

Detour Map CSAH 48 Roudabout_0

Roundabout

CSAH 77/Nokomis Ave


Project Overview:

The City of Nisswa has awarded this project to Anderson Brothers Construction, with work (tree clearing) already underway.  A detour will be set up and can be found in the link below.  Expect delays and please use caution while traveling through the construction zone.

If you have any questions or comments about this project, please contact Joe Dubel with Widseth, Smith and Nolting at: (218) 316-3663  

Project Documents:

CSAH 77/Nokomis Ave. Roundabout Detour Map

CSAH 77 Nakomis Detour Map_0

Culvert Replacement

CSAH 22 over Canyon Creek


Project Overview:

This project is currently out for bid, with work anticipated to begin in August or September.  Once construction operations begin, weekly updates will be provided on this website.  County State Aid Highway (CSAH) 22 will be closed to through traffic while the culverts are being replaced.  A detour will be set up and can be found in the link below.  Expect delays and please use caution while traveling near the construction zone.

If you have any questions or comments about this project, please contact the project manager Jordan Larson or call (218) 824-1110.

Current Update:

  • 10/03/2023 - The new culverts have been installed.  Paving and finishing operations are planned for next week, with the road being scheduled to be open October 20th, weather dependent.  Please continue to use the detour and drive with caution when traveling near the construction zone.

Project Documents:

CSAH 22 Canyon Creek Detour Map_0

Bituminous Seal Coating

CSAH 8, CSAH 10, CSAH 22, CSAH 26, CSAH 36, CSAH 70, CR 136, CR 142, CR 148

FAD - Round Lake Rd, Soder Rd


Project Overview:

A contract has been awarded to Asphalt Technologies Corp. of St. Cloud, MN.  Work is scheduled to start on July 6th, 2023, and last approximately two weeks.   Traffic will be controlled with flaggers.  Expect delays and use caution while traveling through the construction zone.  

 If you have any questions or comments about this project, please contact the project manager Jordan Larson or call (218) 824-1110.

  • 07/18/2023 - Work has been completed. 

Project Documents:

Culvert Replacement

Lower Dean Lake Road


Crow Wing County has entered into a contract with Marvin Tretter Inc. for the replacement of a large culvert on Dean Brook, under Lower Dean Lake Road.  Construction is expected to begin August 9th, 2023, and be completed by September 15th, 2023.  This schedule is subject to variability based upon weather and other factors.

 A temporary road will be constructed on the south side of the existing culvert to allow for access to the west side of the project while the culvert is being replaced.  Please use caution when traveling through the construction zone.

 Please feel free to visit the County’s website or call the County Highway Department at (218) 824-1110 for additional information on the project listed above or with any questions.

Current Update:

  • 09/01/23 - The new culverts have been installed and the the road is open to traffic.   Minor grading and finish work will be completed at some point in the next few weeks.  Please use caution when traveling through the construction zone.