COUNTY HIGHWAY MAINTENANCE ACTIVITIES FOR THE WEEK
OF – MAY 14, 2018
County maintenance
crews will continue crack sealing the below roads this week:
·
CSAH 23, between TH
18 and CSAH 22 – Monday
·
CSAH 48, between SW
4th St. and TH 210 – Tuesday - Thursday
·
CSAH 16, between
CSAH 66 and CSAH 39 – Monday & Tuesday
·
CSAH 36, between TH
6 and Old 114 – Wednesday & Thursday
The County has contracted
Kamco Inc. to crack seal the below roads this week:
·
CSAH 11, between
CSAH 3 and CSAH 4 – Monday & Tuesday
·
CSAH 39, between
CSAH 16 and CSAH 11 – Wednesday & Thursday
·
CR 103, between
CSAH 3 and CSAH 39 – Friday & Saturday
Maintenance crews will be working on one travel
lane and shoulder simultaneously, creating the need to close one lane of
traffic. Signing, flaggers or portable traffic lights will control the traffic
flow through these work areas.
County maintenance crews will be patching potholes
on various county roads Monday -Thursday. Crews will be pulling over and
stopping frequently on the shoulders of the roads, to perform the patching
work. Loose patching material debris may be present.
Motor graders will be smoothing gravel roads Monday
– Wednesday.
Gravel hauling and smoothing will begin Tuesday,
May 15, and will continue throughout week on CR 139 from CSAH 45 – CR 113. DLL Excavating will be performing the work.
Spring weight limits are in effect on all Crow Wing
County roads north of TH 210/18. The restrictions are in effect to reduce
roadway damage from heavy trucks during the spring thaw.
All maintenance work is weather sensitive and is
subject to delay or change.
For further
Information on the county highway system, or to report a roadway issue, please
contact the Highway Department at (218) 824-1110 or visit our Crow Wing County
website at http://www.crowwing.us.